Key Takeaways
- December gold sales remain Allied Gold’s target for Ethiopia’s Kurmuk mine.
- Ethiopian Electric Power’s contractor has begun installing and commissioning automated grid-stabilisation equipment.
- Full grid supply is intended to support normal plant loads without generators.
- Year-end commercial production remains the company’s expectation.
- Allied is advancing technical work and preparing permitting processes for Tsenge development.
- Nine-kilometre Tsenge trend offers additional ore prospects near existing processing infrastructure.
- First-half 2027 resource estimates are expected for Kiftet and Hiccup Hill.
Market Impact
Completing the power system would support higher processing throughput as Kurmuk ramps up. The November 18 update presents sales and commercial production as targets, not completed milestones.
Tsenge exploration aims to expand resources and sustain higher-grade mill feed. Its development remains subject to technical work and approvals.
Key Numbers
- December 2026 — targeted sales start — revenue milestone.
- Year-end 2026 — expected commercial production — operating milestone.
- 300,000 ounces annually — long-term production objective — exploration rationale.
Business Signal
Power completion and additional ore development underpin Allied’s planned production expansion at Kurmuk.