- Allied Gold announced the first gold pour at Ethiopia’s Kurmuk mine on November 9.
- The company targets commercial production by end-2026 and designed operating capacity in early 2027.
- Kurmuk’s output target is 25,000–35,000 ounces in 2026 and 240,000–270,000 ounces in 2027.
- Remaining power infrastructure and full haulage-fleet mobilization are expected to be completed during November.
Why it matters
- The first pour marks a concrete operational milestone beyond commissioning.
- Analysis: Reliable power and fleet deployment will be central to converting initial production into sustained output.
- The production figures remain company forecasts, not achieved volumes.
What to watch
- Confirmation of commercial production and completion of power infrastructure.
- Reported output and recovery rates against the company’s ramp-up targets.
Source: Allied Gold Corporation | 9 November 2026 | Original source