NEWS: Dangote Orders Two Hydrogen Reformers for Ethiopia’s Gode Fertilizer Complex
NEWS: Ethiopia Targets Eight OTC Securities as Treasury Bill Trading Lags
NEWS: Dashen Launches Air Pay for Merchant Payments Without Account Numbers
NEWS: Nyala Insurance Reports Assets Above Birr 7 Billion, Expands Service Strategy
NEWS: IEA Flags Ethiopia’s Electricity Access and Financing Gaps Despite Generation Expansion
NEWS: Ethiopia Processes 1.09 Million Digital Business Services in Three Months
NEWS: Kacha Signs Five-Year Mastercard Agreement to Expand Ethiopian Card Issuance
NEWS: Ethiopia Scores 45% on Electrification Deployment but 38% on Enablers
NEWS: Ethiopia Targets 4.4 Million Off-Grid Household Connections by 2035
NEWS: Ethiopia Signs Canada Market-Access Agreement Ahead of November WTO Talks
Construction & Mining

Dangote Orders Two Hydrogen Reformers for Ethiopia’s Gode Fertilizer Complex

Oct 29, 2026
Dangote Orders Two Hydrogen Reformers for Ethiopia’s Gode Fertilizer Complex

Reported 28 October 2026. Thumbnail: editorial illustration.

Key Takeaways

  • Over 200,000 normal cubic metres of hydrogen per hour is the stated production capacity of the two reformers.
  • Dangote awarded Spain’s Técnicas Reunidas the equipment contract for its Gode ammonia and urea complex.
  • Three million tonnes annually is the fertilizer plant’s planned urea production capacity.
  • Ethiopian natural gas is intended to support domestic fertilizer supply and reduce import-related foreign-exchange spending.
  • Design, procurement, manufacture and free-on-board supply fall within Técnicas Reunidas’ contract scope.
  • 18 months is the maximum equipment supply period stated by the company.
  • TR-Technical will deliver the equipment, with Denmark’s Topsoe providing the technology licence.

Market Impact

  • The award advances equipment procurement for a project intended to substitute fertilizer imports and supply neighbouring markets.
  • The announcement specifies an equipment delivery period, rather than a commissioning date for the entire fertilizer complex.

Key Numbers

  • 2 — hydrogen reformers — contracted equipment.
  • Over 200,000 Nm³/hour — hydrogen capacity — process scale.
  • 3m tonnes/year — planned urea capacity — intended output.
  • 18 months — maximum supply period — delivery timetable.

Business Signal

  • Equipment procurement is progressing, while full-plant operations remain a future milestone.