NEWS: EEU Opens 11 EV Charging Stations, Expanding Operational Network to 14
NEWS: NBE Holds Policy Rate at 16%, Signals Closer Credit Monitoring
NEWS: Adaptation Fund Approves $30 Million for Mandera Triangle Climate Resilience
NEWS: Study Identifies Four Ethiopian Wind Sites, Prioritises Arerti for Grid Access
NEWS: Ethiopia Seeks Nearly $11 Billion in External Financing for Electrification
NEWS: Ethiopian Deposit Insurance Fund Collects Birr 2.61 Billion in Quarterly Premiums
NEWS: ESX Targets 15 Main-Market Listings by June 2027, Expands Pipeline
NEWS: Ethiopia Takes 17% of LDC Services Exports, Overtaking Tanzania
NEWS: Hibret Insurance Raises Profit to Birr 965 Million, Plans Broader Expansion
NEWS: Ethiopia Starts Electric-Truck Charging Study for Strategic Djibouti Trade Corridor
Construction & Mining

Study Identifies Four Ethiopian Wind Sites, Prioritises Arerti for Grid Access

Nov 03, 2026
Study Identifies Four Ethiopian Wind Sites, Prioritises Arerti for Grid Access

Reported November 1, 2026. Thumbnail: editorial illustration.


Key Takeaways

• Four sites show utility-scale wind potential: Gode, Mega, Arerti and Sela Dingay.

• Debre Berhan University researcher Solomon Feleke presented the assessment during Ethiopia’s Water and Energy Week.

• Arerti is recommended for near-term development because consumers and transmission lines are nearby.

• Gode and Mega recorded the strongest wind resources among assessed locations.

• 3MW turbine modelling estimated Gode’s annual output at 9,461MWh.

• Debre Berhan showed marginal suitability at 100 metres.

• Further assessments and Ministry decisions are needed before projects advance.


Market Impact

The findings put grid proximity alongside wind strength in assessing development priorities. Arerti benefits from nearby transmission infrastructure.


Wind generation could complement hydropower during dry periods. The output figures are modelled estimates; the study does not establish operating projects.


Key Numbers

• Four — promising sites — development screening.

• 3MW — modelled turbine capacity — output-assessment basis.

• 132/230kV — nearby Arerti lines — grid-access advantage.


Business Signal

Site selection depends on transmission access as well as wind resources.