Key Takeaways
- The European Investment Bank signed €83 million in financing on 16 November for Ethiopia’s power and telecommunications infrastructure.
- By 2030, the programme aims to halve both how often outages occur and how long they last.
- The energy component accounts for €64.74 million, with €18.26 million for telecommunications.
- Ethiopian Electric Power will rehabilitate and automate substations and upgrade grid dispatch facilities.
- The work includes electricity links with Kenya and Djibouti.
- The programme also covers rehabilitation of the Ashegoda wind farm in Tigray.
- Optical fibre along transmission lines will carry grid communications and provide capacity for telecommunications companies to lease.
Market Impact
The investment addresses two distinct causes of disruption for electricity users: repeated interruptions and the time it takes to restore service. The 2030 target covers both measures.
The financing sits within the wider €270 million RISED programme. Using the same transmission routes for optical fibre gives the utility a way to support grid operations and offer capacity to outside operators.
Key Numbers
- €83 million in signed EIB financing
- €64.74 million for energy
- €18.26 million for telecommunications
Business Signal
Outage frequency and duration are the measures businesses can use to track progress toward the 2030 target.